On a $1,000,000 contract with 10% retainage, the contractor has completed 40% of the schedule of values and received no prior payments. Using AIA G702/G703 logic, what amount is due on this application?
- A$440,000
- B$400,000
- C$40,000
- D$360,000Correct
Why: Amount due = (work completed and stored to date) - retainage - prior payments. Work to date is 40% x $1,000,000 = $400,000; less 10% retainage ($40,000); less $0 prior = $360,000. The withheld $40,000 is released later per the contract.Amount due = value completed/stored - retainage - prior payments; AIA G702/G703 (Ch. 2, Part E)