PrepPass team · Verified against CSLB — C-7 study guide (13E-7) · How we review

Free · printable · no signup

CSLB C-7 Low Voltage Systems (Trade Exam) Exam Cheat Sheet (2026)

A free, printable CSLB C-7 Low Voltage Systems (Trade Exam) exam cheat sheet: the 42 highest-yield points to know, grouped into 7 sections that follow the exam's content areas, each section with its published weight.

  • Free to read, print and keep — no signup, no email, no paywall.
  • 42 of the 42 points carry a citation to the rule they come from.
  • The real CSLB C-7 Low Voltage Systems (Trade Exam) exam: 210 minutes.
  • Prints from your browser (Ctrl-P, or Cmd-P on a Mac) — the navigation, buttons and links drop out of the printed copy.
  • 100 free CSLB C-7 Low Voltage Systems (Trade Exam) practice questions on the same material, every one explained.
  • Last updated: October 2026.

Job Planning and Design

18% of the exam
Study →
C-7 limit
Energy limited and not over 91 volts; telephone, sound, CATV, CCTV, satellite, controls and landscape lighting are named.· Cal. Code Regs. tit. 16 §832.07
Fire alarm
Low voltage fire alarm systems are specifically not included in C-7.· Cal. Code Regs. tit. 16 §832.07
Class 2 and 3
The power source must be listed and marked as Class 2 or Class 3.· Cal. Code Regs. tit. 8 §§2585.1, 2585.2
Horizontal limit
295 feet (90 meters) from patch panel to outlet.· UFC 3-580-01 (2024), para. 2-3.3.2.1
Pull points
No more than 100 feet or 180 degrees of bends between pull boxes.· UFGS 27 10 00 (2025), para. 3.3.1
Separation
Indoor communications cable 2 inches from power conductors unless a barrier or equal method is used.· Cal. Code Regs. tit. 8 §2587.3(d)
Room cooling
Not on time clocks or setbacks; no piping over racks.· UFC 3-580-01 (2024), para. 2-3.1.3.4
Firestopping
Rated penetrations sealed with tested F, T and L rated systems.· UFGS 07 84 00
Existing plant
Test reused pairs before splicing; retag after count transfers.· UFC 3-580-01 (2024), paras. 3-9.2, 3-9.3

Material Selection and Estimation

15% of the exam
Study →
Fiber colors
Single-mode yellow; OM3 aqua; OM4 violet or aqua; OM5 lime green.· UFC 3-580-01 (2024), Table 2-3
Coax
RG-6 drops, RG-11 trunks, no RG-59 on CATV.· UFC 3-580-01 (2024), para. 2-3.5.2
PoE
802.3af 15.4 W; 802.3at 30 W; 802.3bt 60 W and 90 W, at the switch port.· UFC 3-580-01 (2024), Table 2-8; IEEE 802.3 liaison on P802.3bt (May 2017)
Slack
10 feet in the room and 12 inches above the ceiling per cable.· UFGS 27 10 00 (2025), para. 3.4.2
Down payment
Home improvement: no more than $1,000 or 10 percent, whichever is less.· CSLB home improvement contract guide
Changes
Price changes by written change order.· CSLB home improvement contract guide

Wire/Cable Installation and Termination

12% of the exam
Study →
Tension
25 pounds maximum on four-pair copper, monitored.· UFGS 27 10 00 (2025), para. 3.4.2
Bend radius
UTP 4 × diameter; fiber 20 × pulling, 10 × installed.· UFGS 27 10 00 (2025), para. 3.4.2
J-hooks
4 to 5 feet apart, 20 cables maximum, attached to structure.· UFGS 27 10 00 (2025), para. 3.3.4
Untwist
No more than 1/2 inch at the termination.· UFGS 27 10 00 (2025), para. 3.4.2
Labels
Mechanically printed, To/From at both ends; handwritten labels unacceptable.· UFGS 27 10 00 (2025), para. 3.8
Shared boxes
Class 2 and 3 conductors stay out of power boxes and raceways without a barrier.· Cal. Code Regs. tit. 8 §2585.3

Systems Configuration and Installation

16% of the exam
Study →
Rack clearance
36 inches front and back.· UFC 3-580-01 (2024), para. 2-3.1.5.3
Bonding test
Less than 100 milliohms between any two points.· UFGS 27 10 00 (2025), para. 3.11.1.2
Antenna masts
Grounded without a splice in the grounding conductor.· Cal. Code Regs. tit. 8 §2587.5
Cameras
PoE reach 100 meters; 7–15 fps adequate for most security uses.· UFC 4-021-02 (2025)
Audio
25 or 70.7 V lines; size amplifiers at total taps × 1.4.· UFGS 27 51 16
VoIP
150 ms one-way latency bound; separate voice and data networks.· NIST SP 800-58

Testing and Project Closeout

17% of the exam
Study →
Tester levels
IIe Cat 5e, III Cat 6, IIIe Cat 6A at 500 MHz.· UFC 3-580-01 (2024), Table 2-14
Fiber acceptance
Connector 0.5 dB or less; splice 0.3 dB or less.· UFGS 27 10 00 (2025), para. 3.11.1.2
OTDR distance
Time converts to distance with the operator-set group index.· NBSIR 87-3078
Package
Test results with as-built labeling records as one package.· UFGS 27 10 00 (2025), para. 3.11.1
Failures
Corrected before turnover.· UFC 3-580-01 (2024), para. 2-6.5
Commissioning
Required where more than passive equipment is provided.· UFC 3-580-01 (2024), para. 2-7

System Troubleshooting, Repairs, or Replacements

7% of the exam
Study →
Assume energized
Equipment is treated as energized until tested.· Cal. Code Regs. tit. 8 §2320.3
No splices
Horizontal cable is not spliced; replace the run.· UFGS 27 10 00 (2025), para. 3.4.2
Records
Retag cables and terminals after transfers.· UFC 3-580-01 (2024), para. 3-9.3

Safety

15% of the exam
Study →
IIPP
Written program with inspections, investigation, correction and training.· Cal. Code Regs. tit. 8 §§1509, 3203
Under 50 volts
Gloves may be omitted only after a qualified person's determination.· Cal. Code Regs. tit. 8 §2320.2
Locks
Removed only by the person who placed them.· Cal. Code Regs. tit. 8 §2320.5
Ladders
Foot out 1/4 of working length; 36 inches above the landing.· Cal. Code Regs. tit. 8 §3276
Fall protection
Over 7½ feet in construction; free fall no more than 6 feet.· Cal. Code Regs. tit. 8 §1670
Heat
Outdoors: shade above 80°F, high-heat procedures at 95°F. Indoors: the indoor heat standard applies at 82°F.· Cal. Code Regs. tit. 8 §§3395, 3396

Now prove you know them

Reading an outline is not the same as recalling it under exam pressure. Drill the free CSLB C-7 Low Voltage Systems (Trade Exam) questions to find the areas you keep missing, then sit a full timed mock.

Study aid, not a substitute for the official material — always confirm the current rule with CSLB — C-7 study guide (13E-7).

Report