PMI Agile Certified Practitioner (PMI-ACP) — All Questions
AllAgile Principles & MindsetValue-Driven DeliveryStakeholder EngagementTeam PerformanceAdaptive Planning & Problem Detection
4 questions
Adaptive Planning & Problem Detection
'Progressive elaboration' in agile planning means:
- a.Refining plans in more detail as more is known✓
- b.Never planning
- c.Planning only once
- d.Planning everything in detail upfront
Plans are elaborated progressively as understanding grows.
Adaptive Planning & Problem Detection
A burndown chart shows:
- a.Work remaining over time✓
- b.The number of meetings
- c.Defect severity only
- d.Team salaries
A burndown chart tracks remaining work across the iteration.
Adaptive Planning & Problem Detection
Agile planning happens at multiple levels, typically including:
- a.A ten-year fixed plan
- b.Release, iteration, and daily planning✓
- c.Only a single project plan
- d.Only daily plans
Agile plans at release, iteration, and daily horizons.
Adaptive Planning & Problem Detection
A daily standup helps detect problems by:
- a.Surfacing impediments and progress every day✓
- b.Assigning new tasks from a manager
- c.Replacing the retrospective
- d.Providing a detailed status report to managers
The daily standup surfaces impediments and coordinates the team quickly.