SAFe Agilist (Leading SAFe) Practice Test

Frequently asked questions

How many SAFe Agilist (Leading SAFe) practice questions are here?+

A full bank of original SAFe Agilist (Leading SAFe) practice questions across the official content areas, weighted like the real exam, with explanations. Free, no signup.

What is the SAFe Agilist (Leading SAFe) exam like?+

A multiple-choice exam. Practice by topic here, then take the full timed mock exam to gauge readiness.

Are these the real exam questions?+

No. Every question is 100% original, written from public primary sources with explanations. We never copy real exam questions or paid prep material.

Can I study in Chinese or Spanish?+

PrepPass practice is in English, 中文 and Español. The official exam is in English — switch the question language to English any time to rehearse the exact terminology you'll see on test day.

Sample practice questions

A few real questions from this free bank, with full explanations. Use the practice tool above for the whole set.

  1. 1. Lean-Agile Principles & Mindset

    SAFe is founded on:

    • a.Waterfall stage gates
    • b.A single project methodology
    • c.Fixed annual project plans
    • d.Lean and Agile principles

    Answer: d

    Explanation: SAFe is built on Lean-Agile principles and values.

  2. 2. Lean-Agile Principles & Mindset

    In the SAFe House of Lean, the goal at the top is:

    • a.Utilization
    • b.Value
    • c.Individual bonuses
    • d.Documentation

    Answer: b

    Explanation: The goal of the House of Lean is value.

  3. 3. Agile Release Train

    The Agile Release Train (ART) is best described as:

    • a.A long-lived team of agile teams delivering value in a value stream
    • b.A single agile team
    • c.A one-time project
    • d.A portfolio funding model

    Answer: a

    Explanation: An ART is a team of agile teams that continuously delivers value.

  4. 4. Agile Release Train

    The fixed timebox on which an ART delivers is called the:

    • a.Release
    • b.Program Increment (PI)
    • c.Fiscal year
    • d.Sprint

    Answer: b

    Explanation: The Program Increment (PI) is the ART's cadence, usually 8-12 weeks.

  5. 5. PI Planning

    PI Planning is:

    • a.A cadence-based event where all ART teams plan the next PI together
    • b.An optional yearly workshop
    • c.A daily standup
    • d.A portfolio budgeting meeting

    Answer: a

    Explanation: PI Planning is a regular event aligning all ART teams on the upcoming PI.

  6. 6. PI Planning

    The program board created in PI Planning primarily visualizes:

    • a.Source code
    • b.Features, milestones, and cross-team dependencies
    • c.Office seating
    • d.Team salaries

    Answer: b

    Explanation: The program board shows features, milestones, and dependencies across teams.

  7. 7. Lean Portfolio Management

    Lean Portfolio Management funds:

    • a.Individual projects
    • b.Value streams
    • c.Single sprints
    • d.Only executives' initiatives

    Answer: b

    Explanation: LPM funds value streams rather than temporary projects.

  8. 8. Lean Portfolio Management

    A portfolio Epic in SAFe is:

    • a.A defect
    • b.A large initiative requiring analysis (a lightweight business case)
    • c.A daily task
    • d.A single user story

    Answer: b

    Explanation: Epics are large initiatives evaluated with a lightweight business case.

  9. 9. Leading the Transformation

    Lean-Agile leaders are expected to:

    • a.Lead by example and empower teams
    • b.Command and control teams
    • c.Avoid learning the framework
    • d.Make every team decision

    Answer: a

    Explanation: Lean-Agile leaders model the mindset and empower teams.

  10. 10. Leading the Transformation

    Empowering teams to make decisions supports the SAFe principle of:

    • a.Maximizing utilization
    • b.Decentralized decision-making
    • c.Centralized control
    • d.Fixed annual planning

    Answer: b

    Explanation: Empowered teams reflect decentralized decision-making.