Definitions, Theory and Plans
At the master level this area stops asking what a term means and starts asking what it makes you do. A definition triggers a sizing rule, a load figure passes through three tables before it becomes a feeder size, and a transformer nameplate turns into a fault current you have to design around. This chapter follows that chain from the definitions through the equipment room, the Article 120 load calculation and the system theory behind it.
Definitions and approvals that drive design
Two Article 100 terms sit under most of the calculations you will do. A continuous load is one whose maximum current is expected to last 3 hours or more, and that label is what brings in 125 percent sizing of conductors and devices. Demand factor is maximum demand divided by total connected load. It is never more than 1, and it is the Code's way of recognizing that not everything runs at once. Every demand table in Article 120 is an application of that one idea. Be exact about where a feeder starts. Conductors from the secondary of a transformer that is a separately derived source to a panelboard are a feeder, because a feeder runs from service equipment or a derived source to the final branch-circuit overcurrent device. The underground conductors on the utility side of the service point are the service lateral. Two general rules decide many judgment questions. Equipment and conductors are acceptable only if approved, and approved means acceptable to the authority having jurisdiction. Listed or labeled equipment must be installed and used as its listing or labeling instructions say, and field habit does not override them.
Laying out the equipment room
A master is expected to lay out the room, not just measure one panel. Start with depth from Table 110.26(A)(1), entered with voltage to ground. A 480Y/277-volt switchboard facing a concrete wall is a grounded-surface condition and needs 3 feet 6 inches. Live parts on both sides need 4 feet. Then check the size of the equipment. When it is rated 1200 amperes or more and is over 6 feet wide, the working space needs an entrance at each end, each at least 24 inches wide and 6 1/2 feet high, unless one of the single-entrance alternatives (unobstructed egress or doubled depth) applies. When equipment rated 800 amperes or more contains overcurrent devices, any personnel door less than 25 feet from the nearest edge of the working space must swing in the direction of egress and carry listed panic or fire exit hardware. Above the equipment, the dedicated space reaches 6 feet above its top or the structural ceiling, whichever is lower, and a suspended ceiling does not count as structural. On the gear itself, the arc-flash label carries four items: nominal system voltage, arc flash boundary, available incident energy or the minimum level of protective equipment, and the date the assessment was completed. At terminations over 100 amperes, a 90 degrees C conductor still has its ampacity taken at 75 degrees C unless the equipment is listed and identified for more. The 90 degrees C value is available for adjustment and correction only.
Building a load calculation in Article 120
Master calculation questions chain several Article 120 steps, and the wrong answers are what you get by skipping one of them. The exam uses the standard method and ignores exceptions and optional methods unless the question says otherwise, and conductors are copper unless stated. Worked example: a one-family dwelling has 3,200 square feet of floor area, two small-appliance branch circuits and one laundry circuit. Step 1, general lighting at 2 VA per square foot: 3,200 x 2 = 6,400 VA. Step 2, small-appliance circuits at 1,500 VA each: 2 x 1,500 = 3,000 VA. Step 3, laundry: 1,500 VA. Step 4, total: 10,900 VA. Step 5, apply Table 120.45: the first 3,000 VA at 100 percent, and the remaining 7,900 VA at 35 percent, which is 2,765 VA. Step 6, net load: 3,000 + 2,765 = 5,765 VA. The remaining dwelling pieces follow the same pattern. Four or more fastened-in-place appliances may be taken at 75 percent of total nameplate, so 7,400 VA becomes 5,550 VA. For 30 household ranges of 10 kW each, Column C of Table 120.55 gives 15 kW plus 1 kW per range in the 26 through 40 range band, which is 45 kW. For other occupancies, read the unit load first and the demand second. Offices are 1.3 VA per square foot and retail is 1.9. Hotel guest room areas at 1.7 VA per square foot take the first 20,000 VA at 60 percent and the next block at 50 percent, so 68,000 VA nets 36,000 VA. Warehouses take the first 12,500 VA at 100 percent and the rest at 50 percent. Receptacle load takes the first 10 kVA at 100 percent and the remainder at 50 percent. Three pieces of commercial cooking equipment get a 90 percent factor, but the result may not be less than the sum of the two largest. On a feeder neutral with no nonlinear, cooking or dryer loads, the part of the unbalanced load above 200 amperes may be taken at 70 percent, so 350 amperes becomes 305.
Transformers and available fault current
Transformer questions come in pairs: find the full-load current, then use it. Three-phase current is volt-amperes divided by 1.732 times the line voltage. A 75 kVA unit draws about 90 amperes at 480 volts and delivers about 208 amperes at 208 volts. A 112.5 kVA unit is 135 amperes on the primary and 312 on the secondary. Available fault current at the secondary terminals, assuming an infinite primary source, is the secondary full-load current divided by the impedance as a decimal. The 112.5 kVA, 208-volt transformer at 2 percent impedance gives 312.3 / 0.02, about 15,617 amperes. Notice what impedance does: a 300 kVA, 480-volt unit at 5 percent yields only about 7,217 amperes, less than half of the smaller transformer's figure. Ratio questions are simpler. A 480 to 120 volt transformer has a 4:1 ratio, and current moves the opposite way, so 10 amperes on the primary is 40 amperes on the secondary.
Power factor, harmonics and balance
Think of the power triangle. Real power in kW and reactive power in kVAR are the two legs, and apparent power in kVA is the hypotenuse. Power factor is kW divided by kVA, and it is also the cosine of the angle by which current lags voltage, so a 30 degree lag is about 0.87. A load of 80 kW and 100 kVA has a power factor of 0.8 and, by the square-root relationship, 60 kVAR. To correct that 80 kW load from 0.80 to 0.95, multiply the kW by the difference between the two tangents the question supplies: 80 x (0.750 - 0.329) = 33.7 kVAR of capacitors. Real power always includes the power factor: 1.732 x 480 x 50 x 0.85 is 35,333 watts three-phase, and 240 x 30 x 0.90 is 6,480 watts single-phase. Motor questions convert first: one horsepower is 746 watts, so 10 horsepower out for 8,300 watts in is about 90 percent efficiency. On a 4-wire wye system with nonlinear loads, third-order harmonic currents are in phase on all three legs and add in the neutral, which is how a neutral can carry more than a phase conductor. On a high-leg delta, the high leg measures 208 volts to neutral on a 240-volt system and must not serve line-to-neutral loads.
Voltage drop, plans and safe work
Use voltage drop as a design check. Single-phase drop is 2 x K x I x L divided by circular mils, and three-phase uses 1.732 in place of 2. A 480-volt feeder carrying 60 amperes 200 feet on 4 AWG copper, 41,740 circular mils with K at 12.9, drops about 6.4 volts, which is 1.3 percent. Solved for area, a 240-volt circuit at 24 amperes and 150 feet held to 7.2 volts needs 12,900 circular mils, and 8 AWG is the smallest conductor that provides it. Plan questions are plain. A one-line diagram shows each circuit or set of conductors as a single line with standard symbols. A rough-in inspection happens before wiring is concealed. NFPA 70E is the standard for safety-related work practices, including arc-flash and shock protection. The preferred condition for any work is an electrically safe one: de-energized, locked out, and verified.
Keep going: the full Texas Master Electrician (TDLR / PSI, 2026 NEC) guide covers every section of the exam. Texas Master Electrician Exam — Open-Book Study Guide (2026 NEC) — PDF + EPUB, $14.99 · 14-day refund →
Want the dense 47-page printable for exam week? Texas Master Electrician (TDLR / PSI, 2026 NEC) cheat sheet PDF — $9.99 →

Practice stays free. The full Texas Master Electrician (TDLR / PSI, 2026 NEC) study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.