Motors, Compressors and Generators: Designing the Complete Circuit
The master exam assumes you know the basic motor percentages and tests what happens around them: special conductor multipliers, the ceiling when a motor will not start, feeders and services carrying several motors, and hermetic compressors under Article 440. Treat each problem as a design sequence. Identify the type of motor, pick the correct current, then apply the percentage that belongs to that component.
Choosing the design current
Every motor calculation begins with a decision about which current governs. For a general-application motor, 430.6(A)(1) sends you to the full-load current tables, Tables 430.247 through 430.250, for conductors and for short-circuit and ground-fault protection. The nameplate is reserved for separate overload protection. Table 430.250 is the one you will open most. Know how to read it quickly: at 460 volts three-phase it lists 34 amperes for 25 horsepower, 40 for 30, 52 for 40 and 65 for 50. Questions written at 480 volts use the same column. Two motor types break the pattern. A torque motor normally works at standstill, so 430.6(B) treats its nameplate locked-rotor current as the rated current for the branch-circuit conductors. The horsepower tables do not apply to it. A motor on duty-cycle service is sized from nameplate current under Table 430.22(E), covered below. On the exam, a question that gives a table current and a nameplate current is checking whether you assign each to the right component. A question that gives only one current and names the component expects you to use it as given.
Conductor multipliers beyond 125 percent
The base rule in 430.22 is 125 percent of the table current for a single continuous-duty motor, so a 40-horsepower motor at 52 amperes needs 65 amperes of conductor ampacity. The master exam goes further and asks about the cases where the multiplier changes because the current in the conductor is not the ordinary line current. A dc motor fed from a rectifier is the first case. Rectified single-phase power has heavy ripple, which heats the conductors more than smooth dc of the same average value. Under 430.22(A), the conductors between a single-phase full-wave rectifier and the motor are sized at 150 percent of full-load current. A 10-horsepower, 240-volt dc motor at 38 amperes needs 38 x 1.5 = 57 amperes. The half-wave figure is 190 percent, and it is a standard wrong choice in full-wave questions. The second case is a wye-start, delta-run motor. Between the controller and the motor there are two sets of conductors and each carries only part of the line current, so 430.22(C) sizes them at 72 percent of the motor full-load current. The 125 percent rule still applies on the line side of the controller. Do not confuse 72 percent with the 62.5 percent figure, which belongs to part-winding motors. The third case is duty-cycle service. Table 430.22(E) gives a percentage of nameplate current by type of duty and motor time rating. Intermittent duty with a 15-minute rated motor is 85 percent, so a 40-ampere nameplate requires 34 amperes.
Protection limits and the ceiling when a motor will not start
Table 430.52(C)(1) sets the maximum branch-circuit short-circuit and ground-fault device. For squirrel-cage motors it allows 175 percent for dual-element time-delay fuses, 250 percent for inverse-time breakers and 300 percent for non-time-delay fuses. An inverse-time breaker on a wound-rotor motor is held to 150 percent. Where the product is not a standard rating in Table 240.6(A), 430.52(C)(1)(a) permits the next higher standard size. Where the product is already standard, that is the answer: a 40-ampere motor gives exactly 100 amperes for the breaker and exactly 70 amperes for the dual-element fuse. Stepping up from an exact standard value is a master-level trap. The design question is what to do when the table device trips on starting. The Code allows an increase, with a hard ceiling. For an inverse-time breaker the ceiling is 400 percent of full-load current where that current is 100 amperes or less, and 300 percent where it is over 100 amperes. A 50-horsepower motor at 65 amperes has a normal breaker of 175 amperes. If that trips on starting, the limit is 65 x 4 = 260 amperes. This ceiling may not be exceeded, so the largest usable standard size is 250 amperes, not 300. So there are two rounding directions in one section. The normal table calculation rounds up. The will-not-start ceiling rounds down.
Overload protection as a nameplate decision
Overload sizing under 430.32(A)(1) is a two-way sort on the nameplate markings. A marked service factor of 1.15 or greater, or a marked temperature rise of 40 degrees C or less, earns 125 percent of nameplate current. Either marking alone is enough: a motor marked 40 degrees C with no service factor and a 52-ampere nameplate is allowed 65 amperes. A motor with neither marking is held to 115 percent, so 28 amperes gives 32.2 amperes, and a motor marked service factor 1.0 and 50 degrees C rise with 18 amperes gives 20.7 amperes. Read the markings before you multiply. Questions state a service factor of 1.0 or a 50 degree rise to see whether you notice that neither one qualifies. An integral thermal protector is different in two ways. Its limit under 430.32(A)(2) is based on the table full-load current, and the percentage falls as the motor gets larger: 170 percent up to 9 amperes, 156 percent from 9.1 through 20 amperes, and 140 percent above 20 amperes. Table 430.37 requires three overload units, one per phase, on a three-phase ac motor.
Feeders and services with several motors: worked example
A feeder supplies only three 460-volt, three-phase motors with full-load currents of 40, 27 and 14 amperes. Their branch-circuit breakers are 100, 70 and 35 amperes. Find the largest standard feeder overcurrent device. Step 1. Identify the largest branch-circuit short-circuit and ground-fault device: 100 amperes. This is the 40-ampere motor at 250 percent. Step 2. Add the full-load currents of the other motors, not their breaker ratings: 27 + 14 = 41 amperes. Step 3. Apply 430.62(A): 100 + 41 = 141 amperes. Step 4. This is a maximum with no allowance to round up. The largest standard rating that does not exceed 141 is 125 amperes. The 150-ampere choice rounds up, and larger wrong choices come from adding the other breakers or a 125 percent factor. The feeder conductors use a different rule, 430.24: 125 percent of the highest-rated motor plus the full-load currents of the others. For a 50-horsepower motor at 65 amperes and a 30-horsepower motor at 40 amperes, that is (65 x 1.25) + 40 = 121.25 amperes. For three motors at 34, 28 and 22 amperes it is 42.5 + 50 = 92.5 amperes. The same idea reaches the service calculation through 120.50. When the motor loads are already in the total at 100 percent, the largest-motor step adds only the extra 25 percent. With a 40-ampere largest motor you add 0.25 x 40 = 10 amperes. Adding 50 amperes counts that motor twice.
Hermetic compressors and generators
A hermetic refrigerant motor-compressor has no horsepower rating to take to the tables, so Article 440 works from its rated-load current or its branch-circuit selection current. Conductors to a single compressor under 440.32 are 125 percent of that current: 24 amperes needs 30 amperes and 28 amperes needs 35 amperes. Where a compressor shares the circuit with another motor, 440.33 adds the currents plus 25 percent of the largest. A 20-ampere compressor with a 3-ampere fan needs 20 + 3 + 5 = 28 amperes. The short-circuit and ground-fault device under 440.22(A) starts at 175 percent of rated-load current. For 24 amperes that is 42 amperes, which is not a standard rating. Exception No. 1 permits the next higher standard rating, 45 amperes, but without the exception the device could not exceed 42 amperes. This matters because the exam ignores exceptions and optional methods unless the question tells you to use one, and it assumes copper conductors unless stated. Read whether the compressor question invokes the exception before you round up. For packaged equipment the nameplate does much of the work. Under 440.4(B) it is marked with a minimum circuit ampacity, which sizes the supply conductors, and the marked maximum overcurrent device rating sizes the fuse or breaker. Generators have one calculation here. Under 445.13(A) the output conductors from the terminals to the first overcurrent device need at least 115 percent of the generator nameplate current.
Keep going: the full Texas Master Electrician (TDLR / PSI, 2026 NEC) guide covers every section of the exam. Texas Master Electrician Exam — Open-Book Study Guide (2026 NEC) — PDF + EPUB, $14.99 · 14-day refund →
Want the dense 47-page printable for exam week? Texas Master Electrician (TDLR / PSI, 2026 NEC) cheat sheet PDF — $9.99 →

Practice stays free. The full Texas Master Electrician (TDLR / PSI, 2026 NEC) study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.