A contractor who pays workers LESS than the required prevailing wage on a public works project is subject to:

a.A written warning from the awarding body for the first offense
b.Immediate revocation of the contractor's CSLB licence by law
c.Back wages plus a penalty per worker per day of violation
d.Forfeiture of the contract price to the public entity

Explicación

Labor Code §1775(a) makes the contractor pay the difference between what was paid and the prevailing rate, and adds a civil penalty of up to $200 for each worker for each calendar day of underpayment. Nothing in the statute offers a first-offense warning. Licence revocation is a CSLB proceeding under B&P §7110 that may follow, but it is neither automatic nor what §1775 imposes. Forfeiting the contract price is not a prevailing wage remedy; under §1726 the awarding body withholds only the assessed amounts.

Referencia Legal: Labor Code §1775(a)

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar