Seguros y GravámenesPregunta 1508 de 1605

Compared to a mechanics lien, a key ADVANTAGE of a stop payment notice for a lower-tier claimant is that it:

a.Never requires a bond
b.Automatically doubles the recovery amount
c.Reaches undisbursed construction funds and can be pursued without foreclosing on the owner's real property
d.Requires no preliminary notice

Explicación

A stop payment notice reaches undisbursed construction funds held by the owner or lender, avoiding a foreclosure suit against the real property. It generally still requires a valid preliminary notice, and a stop notice to a lender requires a 125% bond, but it offers a distinct fund-based remedy.

Referencia Legal: Civ. Code §8500

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar