Seguros y GravámenesPregunta 1515 de 1605

A notice of completion was recorded on July 1. An unpaid drywall subcontractor wants to record a mechanics lien. The last day to record is approximately:

a.July 5
b.August 30 (60 days)
c.September 29 (90 days)
d.July 31 (30 days)

Explicación

Under Civil Code §8414, once a notice of completion is recorded, a claimant other than the direct contractor must record within 30 days. Counting 30 days from July 1 lands at the end of July. Only the direct contractor would get 60 days.

Referencia Legal: Civ. Code §8414