A notice of completion was recorded on July 1. An unpaid drywall subcontractor wants to record a mechanics lien. The last day to record is approximately:
a.July 5
b.August 30 (60 days)
c.September 29 (90 days)
d.July 31 (30 days)
Explicación
Under Civil Code §8414, once a notice of completion is recorded, a claimant other than the direct contractor must record within 30 days. Counting 30 days from July 1 lands at the end of July. Only the direct contractor would get 60 days.
Referencia Legal: Civ. Code §8414Practica las 1632 preguntas gratis — sin registro.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Preguntas relacionadas de este tema
- In a hold-harmless agreement, the 'indemnitor' is the party that:
- Why serve the preliminary notice at the start of a project, when payment is still arriving on time?
- Which statement about surety bonds is TRUE?
- The 'your work' exclusion in a CGL policy means the policy generally will NOT pay to:
- A mechanics lien attaches to:
- Which document actually grants an owner additional insured status under the general contractor's liability policy?
Última revisión: · proceso editorial
Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)