Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:

a.Makes the GC the policyholder
b.Extends the mechanics lien deadline
c.Guarantees the sub will never be canceled
d.Confirms required coverage is in force before the sub creates any exposure on the job

Explicación

Obtaining the certificate before work begins verifies the sub's required coverage is in place before any liability-creating work occurs. It is a front-end risk-management control, though the GC should also require additional insured endorsements for actual coverage.