Seguros y GravámenesPregunta 1564 de 1605
A design professional (e.g., architect) who provided services for a private work of improvement authorized by the owner:
a.Never has lien rights under any circumstances
b.Can only file a stop payment notice, never a lien
c.Must carry builder's risk insurance instead
d.May have mechanics lien rights for the value of the services if statutory conditions are met
Explicación
Design professionals who furnish services for a work of improvement are among those the mechanics lien law protects (Civil Code §8400, and design professional lien provisions), provided statutory conditions and notices are satisfied. They contribute value to the improvement.
Referencia Legal: Civ. Code §8410Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Which best describes the difference between the payment bond and the performance bond on the SAME project?
- A mechanics lien on a private project should describe the property with:
- 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
- An owner asks the contractor to provide a certificate of insurance naming the owner as additional insured. For the owner to actually have that status, the certificate must be accompanied by, or reflect:
- A stop payment notice, unlike a mechanics lien, does NOT need to be:
- A contractor hires day laborers and pays them cash, believing they are 'independent contractors,' and carries no workers' compensation. If a laborer is injured, the contractor most likely:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)