Contratos y EjecuciónPregunta 878 de 1632

A 'retention' (retainage) provision in a construction contract generally allows the owner to:

a.Take ownership of the contractor's tools until completion
b.Charge the contractor a fee for administering payments
c.Withhold part of each payment until work is accepted
d.Delay paying for completed work until the warranty expires

Explicación

A retention or retainage clause lets the owner withhold part of each progress payment as security that the contractor will finish properly and correct defects, releasing it after satisfactory completion or acceptance (c). The percentage is no longer open-ended: Public Contract Code §7201 caps most public works at 5%, and Civil Code §8811 caps private works at 5% for contracts entered into on or after January 1, 2026, leaving the older 10% practice only for pre-2026 contracts and the statute's narrow exceptions. (a) is wrong because retention is money held back, not a claim on the contractor's property. (b) confuses retention with an administrative charge — retention is the contractor's own earned money, held temporarily, not a fee. (d) is wrong because the withheld money is paid when the conditions are met; a warranty period does not license the owner to keep deferring it.

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar