Contratos y EjecuciónPregunta 886 de 1605
A contractor and owner sign a contract, then later sign a separate written agreement that clearly changes the completion date and adds $6,000 in scope. This later signed agreement is best described as:
a.A valid written contract modification supported by new consideration (the added scope and price)
b.An unenforceable oral modification
c.A tort claim
d.A violation of the parol evidence rule
Explicación
A written, signed agreement that changes the completion date and adds new scope for additional payment is a valid modification of the original contract, supported by fresh consideration because both the added work and the added payment are new, bargained-for exchanges. It is written, not an unenforceable oral change, and it is a contract matter, not a tort. The parol evidence rule does not bar it, since that rule addresses prior or contemporaneous statements, not a later signed modification.
Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- An 'indemnification' (hold harmless) clause in a construction contract generally requires one party to:
- A 'severability' (savings) clause provides that if one provision of the contract is found invalid:
- An 'attorney fees' clause in a contract typically provides that:
- In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:
- An owner and contractor dispute whether a certain task was included in the fixed price. The contract's clear, integrated scope of work does not list that task. Under general interpretation principles, the task is most likely:
- A key reason a contractor should ensure the person signing a contract has authority to bind the property is that:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)