The main financial risk of taking on a job much larger than a contractor's usual size is:

a.Depreciation on the equipment stops completely
b.The CSLB upgrades the licence class held
c.Sales tax on those materials is waived
d.Too little working capital to carry the costs

Explicación

A job several times the usual size demands payroll and material money weeks before the first progress payment lands, and retention holds part of it back longer still, so the contractor can run dry mid-project on a job that is profitable on paper. Depreciation follows the asset's schedule and is unaffected by job size. Classification follows the trade the contractor is qualified in and is never upgraded automatically. And material tax is owed on every job whatever its size.

Practica las 1632 preguntas gratis — sin registro.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Equipo de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)
Reportar