Finanzas ComercialesPregunta 1230 de 1632

A contractor factors (sells) $50,000 of receivables to a factor who advances 90% now and charges a 3% fee on the face amount. How much cash does the contractor receive up front, and what is the fee?

a.$50,000 advance; $1,500 fee
b.$45,000 advance; $1,500 fee
c.$45,000 advance; $3,000 fee
d.$47,000 advance; $0 fee

Explicación

Advance = 90% x $50,000 = $45,000 up front. Fee = 3% x $50,000 = $1,500. Factoring speeds cash but at a cost, reducing the effective amount collected.