A good estimate should include a contingency allowance primarily to:
a.Increase the contractor's guaranteed profit
b.Reduce the sales tax on materials
c.Cover unforeseen conditions and estimating uncertainty
d.Pay the CSLB renewal fee
Explicación
A contingency is money added to the estimate to absorb unforeseen conditions, minor scope changes, and normal estimating uncertainty. It protects the contractor from small surprises without renegotiating the contract; it is not extra profit.
Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
- A painting job covers 2,400 square feet. One gallon covers 350 sq ft. How many gallons (rounded up to full cans) are needed for two coats?
- A subcontractor bids $18,000. The general contractor adds a 12% markup on that subcontract. What is the marked-up amount billed to the owner for that scope?
- Working capital is calculated as:
- A contractor has current assets of $150,000 and current liabilities of $90,000. What is his working capital?
- Poor cash flow on a construction project is MOST often caused by:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)