保险与留置权第 1574 / 1605 题
A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for:
a.Nothing; releases are optional
b.Triple the project value automatically
c.Damages, because the claimant must execute and record a release once the claim is satisfied
d.Only the contractor's lost profit
解析
Once a lien is satisfied, the claimant must release it. Under the mechanics lien law, a claimant who wrongfully fails or refuses to release a paid lien can be liable to the owner for resulting damages. Prompt release of satisfied liens is required.
法律依据: Civ. Code §8420免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
- A claim on a private-project payment bond generally requires the claimant to have:
- The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
- The '$25,000' figure most commonly associated with California contractor licensing refers to the: