保险与留置权第 1572 / 1605 题
A claim on a private-project payment bond generally requires the claimant to have:
a.Posted a 125% bond
b.Given the preliminary notice required for lien rights (unless excused), because bond rights parallel lien rights
c.Recorded a mechanics lien first
d.Obtained a court judgment first
解析
Under Civil Code §8600 et seq., a claimant's right to recover on a private-project payment bond generally depends on having given the preliminary notice required to preserve lien rights (unless excused, e.g., laborers). The bond claim parallels the lien claim's notice conditions.
法律依据: Civ. Code §8600免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
- The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
- A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for:
- The '$25,000' figure most commonly associated with California contractor licensing refers to the: