保险与留置权第 1572 / 1605 题

A claim on a private-project payment bond generally requires the claimant to have:

a.Posted a 125% bond
b.Given the preliminary notice required for lien rights (unless excused), because bond rights parallel lien rights
c.Recorded a mechanics lien first
d.Obtained a court judgment first

解析

Under Civil Code §8600 et seq., a claimant's right to recover on a private-project payment bond generally depends on having given the preliminary notice required to preserve lien rights (unless excused, e.g., laborers). The bond claim parallels the lien claim's notice conditions.

法律依据: Civ. Code §8600

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈