保险与留置权第 1569 / 1605 题
Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
a.Certificate of insurance
b.Mechanics lien
c.Stop payment notice
d.Payment bond claim
解析
A mechanics lien ultimately requires a foreclosure action against the owner's real property to collect, making it more cumbersome than a stop payment notice (reaching funds) or a payment bond claim (reaching a surety). Claimants often pursue funds or bonds first.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A stop payment notice, unlike a mechanics lien, does NOT need to be:
- A contractor hires day laborers and pays them cash, believing they are 'independent contractors,' and carries no workers' compensation. If a laborer is injured, the contractor most likely:
- A supplier first delivered materials on Day 1 but did not serve its preliminary notice until Day 40. Under the notice rules, the supplier may claim a lien/stop-notice for materials furnished:
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
- A claim on a private-project payment bond generally requires the claimant to have: