保险与留置权第 1566 / 1632 题
A stop payment notice, unlike a mechanics lien, does NOT need to be:
a.Supported by a valid claim
b.Given by someone who furnished work
c.Served on the correct party
d.Recorded with the county recorder
解析
A stop payment notice is served, not recorded; it directs the owner or lender to withhold funds. A mechanics lien, by contrast, is recorded against the property. Both require a valid underlying claim by someone who furnished work and proper service.
法律依据: Civ. Code §8500免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
- An architect provided design services for a private work of improvement, authorized by the owner. The architect:
- An owner wants to be an additional insured on the contractor's policy. For the owner actually to have that status, the certificate must be accompanied by:
- A contractor pays day laborers in cash, calls them independent contractors, and carries no workers' compensation. A laborer is injured. The contractor most likely:
- A supplier first delivered materials on Day 1 but served its preliminary notice on Day 40. For which materials may it claim?
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)