保险与留置权第 1571 / 1605 题
A general contractor's CGL policy typically will NOT respond to which claim?
a.The GC's crane damaging an adjacent building
b.A visitor tripping over the GC's debris and breaking an arm
c.A pedestrian struck by falling material
d.The GC's own employee injured while framing (that is workers' compensation)
解析
Injuries to the contractor's own employees are covered by workers' compensation, not CGL. The CGL responds to third-party bodily injury and property damage — visitors, neighbors, pedestrians — arising from the contractor's operations.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A supplier first delivered materials on Day 1 but did not serve its preliminary notice until Day 40. Under the notice rules, the supplier may claim a lien/stop-notice for materials furnished:
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A claim on a private-project payment bond generally requires the claimant to have:
- The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they:
- A lien claimant who has been paid in full but refuses to release a recorded mechanics lien may be liable to the owner for: