保险与留置权第 1570 / 1632 题
On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
a.The claimant may still record within 60 days, as the direct contractor may
b.The claimant loses the mechanics lien, but other remedies may survive
c.The claimant may record within 90 days from actual completion instead
d.The claimant has 90 days from recording to file suit on the lien
解析
Civil Code §8414 gives a claimant other than the direct contractor 30 days after a recorded notice of completion; miss it and the lien remedy is gone, though a payment bond claim, a timely stop payment notice, or a plain breach-of-contract action may remain. (a) borrows the direct contractor's 60-day period under §8412, which is not available to lower-tier claimants. (c) is the no-notice rule the recording displaced. (d) states the §8460 deadline for suing on a lien already recorded, which never revives a lien that was recorded too late.
法律依据: Civil Code §8414 / §8460免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- A contractor pays day laborers in cash, calls them independent contractors, and carries no workers' compensation. A laborer is injured. The contractor most likely:
- A supplier first delivered materials on Day 1 but served its preliminary notice on Day 40. For which materials may it claim?
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- A general contractor's CGL policy typically will NOT respond to which claim?
- A claim on a private-project payment bond generally requires the claimant to have:
- The most accurate reason insurance and surety bonds are BOTH used on construction projects is that they: