On a private work with a construction lender, for a stop payment notice to bind the LENDER to withhold funds, the claimant generally must:

a.Send the lender a written demand, itemised and signed under oath
b.Obtain a court order directing the lender to withhold the funds
c.Record the stop payment notice with the county recorder's office
d.Serve a bonded notice, bonded at 125 percent of the claim

解析

Civil Code §8532 obligates a construction lender to withhold only on a bonded stop payment notice, accompanied by a surety bond of 125 percent of the claim; the bond protects the lender if the claim turns out to be bad. (a) is the closest trap: form and verification matter, but no amount of formality substitutes for the bond. (b) reverses the order — the notice works without going to court, which is why it is useful. (c) borrows mechanics lien practice, where recording is the operative act; a stop payment notice is served, not recorded. A notice to the owner under §8534 needs no bond.

法律依据: Civil Code §8506 / §8532

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈