After recording a mechanics lien, within what period must the claimant file a lawsuit (action) to foreclose the lien, or the lien becomes unenforceable?
a.Within 30 days of recording
b.Within 90 days after recording of the lien
c.Within 60 days of recording
d.Within 6 months, but only if the owner objects
解析
Civil Code §8460 requires the claimant to commence an action to foreclose the mechanics lien within 90 days after recording. If no suit is filed in time (absent a recorded extension), the lien expires and is unenforceable.
法律依据: Civ. Code §8460免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- Which claimant is generally NOT required to serve a preliminary notice to preserve a mechanics lien?
- A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?
- A payment dispute is resolved and the claimant has been paid. What does it record to clear the mechanics lien from the property?
- A 'stop payment notice' (formerly 'stop notice') is a remedy that allows an unpaid claimant to reach:
- On a private work with a construction lender, for a stop payment notice to bind the LENDER to withhold funds, the claimant generally must:
- On a private commercial project the direct contractor furnishes a payment bond. Its primary purpose is to:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)