A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?

a.On every subcontractor on the job
b.On the owner, within 20 days, to preserve any lien right
c.On the CSLB registrar
d.Only on a construction lender, if one exists; a preliminary notice is otherwise not required to the owner because of the direct contract

解析

A direct contractor with a contract with the owner need not serve the owner a preliminary notice, but under Civil Code §8200 must give notice to a construction lender (if any) to preserve rights against construction funds. The direct owner contract itself satisfies the notice purpose as to the owner.

法律依据: Civ. Code §8410