A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?

a.On every subcontractor and supplier working under the prime contract
b.On the owner, within 20 days, to preserve any lien right
c.On no one, because a direct contract dispenses with all notice
d.On the construction lender only, if the project has one

解析

Civil Code §8200(e) excuses a direct contractor from serving the owner — the contract itself gives the owner notice — but the direct contractor must still give the preliminary notice to a construction lender to preserve rights against the construction funds. (a) inverts the flow: notice runs up the chain toward the people who control the money, not down it. (b) applies the general rule without reading the exception, and is the trap for anyone who memorised '20 days' alone. (c) over-reads the exception, which covers only the owner and not the lender.

法律依据: Civil Code §8200(e)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈