保险与留置权第 1471 / 1605 题
On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?
a.The owner (or reputed owner), the direct contractor, and the construction lender (if any)
b.The direct (prime) contractor only
c.The construction lender only
d.The owner only
解析
Civil Code §8200 requires a claimant without a direct contract with the owner to serve the preliminary notice on the owner (or reputed owner), the direct contractor, and the construction lender, if any. Missing a required recipient jeopardizes lien and stop payment notice rights.
法律依据: Civ. Code §8200免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
- Which type of claimant is generally NOT required to serve a Preliminary Notice to preserve a mechanics lien?
- A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?
- To remove a recorded mechanics lien from the property when a payment dispute is resolved, the contractor typically records a: