保险与留置权第 1468 / 1605 题
After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
a.90 days after recording of the notice of completion
b.60 days after recording of the notice of completion
c.30 days after recording of the notice of completion
d.10 days after recording of the notice of completion
解析
Under Civil Code §8414, once a notice of completion (or cessation) is recorded, a claimant other than the direct contractor must record its lien within 30 days. The direct contractor gets 60 days after that notice. Absent any such notice, everyone has 90 days after completion.
法律依据: Civ. Code §8414免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- 分包商的商业一般责任(CGL)保单为分包商的疏忽工作向主承包商提供'附加被保险人'身份。如果第三方受伤并起诉分包商和主承包商,根据加州法律:
- A framing subcontractor supplied labor and materials to a private residential remodel but was never paid. Which of the following best describes who is entitled to record a mechanics lien?
- On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
- On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?