保险与留置权第 1467 / 1605 题
On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
a.Within 120 days after completion
b.Within 90 days after completion
c.Within 30 days after completion
d.Within 60 days after completion
解析
Civil Code §8412 gives a direct contractor 90 days after completion of the work of improvement to record a mechanics lien when no notice of completion or cessation has been recorded. The shorter deadlines apply only after such a notice is recorded.
法律依据: Civ. Code §8412免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- 一位房主就家庭住宅未完成的工作对持照承包商获得$40,000判决。该承包商的$25,000执照保证金还被未付的框架工($8,000工资索赔)和非住宅商业业主($30,000损害赔偿)追索。根据§7071.11优先级方案,房主可以预期获得约:
- 分包商的商业一般责任(CGL)保单为分包商的疏忽工作向主承包商提供'附加被保险人'身份。如果第三方受伤并起诉分包商和主承包商,根据加州法律:
- A framing subcontractor supplied labor and materials to a private residential remodel but was never paid. Which of the following best describes who is entitled to record a mechanics lien?
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?