An unpaid framing subcontractor furnished labor and materials to a private remodel. Who is entitled to record a mechanics lien?
解析
Civil Code §8400 gives a lien right to a person that provides work authorized for a work of improvement, and lists the direct contractor, subcontractor, material supplier, equipment lessor, laborer, and design professional; §8404 defines authorized work as work requested or agreed to by the owner, or authorized by a direct contractor, subcontractor, architect, project manager, or other person having charge of part of the work. The framing subcontractor is squarely inside that. (b) is the limit that matters: a creditor who contributed nothing to the improvement, such as the contractor's landlord or lender, has no lien. (a) and (c) shrink the class to a single tier, which would leave every subcontractor and supplier without the remedy the chapter was written for.
法律依据: Civ. Code §8400 / §8404免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- 业主希望解除登记在房产上的$60,000机械师留置权,以便出售或再融资该房产。根据Civil Code §8424,业主可通过登记金额为以下数额的留置权解除保证金获得留置权解除:
- 针对某承包商25,000美元执照保证金的索赔总额远超25,000美元:一名住宅业主索赔40,000美元,一名未获付款的木工索赔8,000美元工资,一名商业物业业主索赔30,000美元。根据Bus. & Prof. Code §7071.11,该保证金如何分配?
- 分包商的商业一般责任(CGL)保单为分包商的疏忽工作向主承包商提供'附加被保险人'身份。如果第三方受伤并起诉分包商和主承包商,根据加州法律:
- On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
最近核对: · 审核流程