保险与留置权第 1474 / 1605 题
To remove a recorded mechanics lien from the property when a payment dispute is resolved, the contractor typically records a:
a.Mechanics lien release (release of mechanics lien)
b.Notice of cessation
c.Notice of non-responsibility
d.Preliminary notice
解析
When a lien is paid, satisfied, or otherwise released, the claimant records a release of mechanics lien (Civil Code §8424 addresses release bonds; the recorded release clears title). A notice of non-responsibility and notice of cessation serve entirely different functions.
法律依据: Civ. Code §8424免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?
- Which type of claimant is generally NOT required to serve a Preliminary Notice to preserve a mechanics lien?
- A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?
- After recording a mechanics lien, within what period must the claimant file a lawsuit (action) to foreclose the lien, or the lien becomes unenforceable?
- A 'stop payment notice' (formerly 'stop notice') is a remedy that allows an unpaid claimant to reach:
- On a private work with a construction lender, for a stop payment notice to bind the LENDER to withhold funds, the claimant generally must: