保险与留置权第 1474 / 1605 题

To remove a recorded mechanics lien from the property when a payment dispute is resolved, the contractor typically records a:

a.Mechanics lien release (release of mechanics lien)
b.Notice of cessation
c.Notice of non-responsibility
d.Preliminary notice

解析

When a lien is paid, satisfied, or otherwise released, the claimant records a release of mechanics lien (Civil Code §8424 addresses release bonds; the recorded release clears title). A notice of non-responsibility and notice of cessation serve entirely different functions.

法律依据: Civ. Code §8424