A city hires a contractor for a $50,000 public sidewalk repair. Regarding prevailing wages, the contractor must:
a.Pay only minimum wage because it is repair work
b.Pay prevailing wage only to apprentices
c.Pay at least the prevailing wage rates determined by the DIR to all covered workers
d.Pay any wage the workers accept
解析
Because the project is public work over $1,000 (Labor Code §1771), the contractor must pay all covered workers at least the DIR-determined prevailing wage rates for their classifications, including both the base rate and fringe benefit amounts. Repair work is expressly covered.
法律依据: Labor Code §1771免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- If the Labor Commissioner issues a Civil Wage and Penalty Assessment for prevailing wage violations, the contractor generally may:
- A public agency rejects the lowest bid because the bidder failed to acknowledge a required addendum and omitted a mandatory subcontractor listing. This bid was properly rejected as:
- Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
- On a federal public works project, the prevailing wage requirement comes primarily from the:
- The performance bond on a public works project protects the: