公共工程第 1598 / 1605 题
On a federal public works project, the prevailing wage requirement comes primarily from the:
a.Uniform Commercial Code
b.California Labor Code only
c.Davis-Bacon Act (federal), which requires prevailing wages on covered federal construction
d.Contractors State License Law
解析
On federal construction contracts above the threshold, the Davis-Bacon Act requires payment of locally prevailing wages and fringe benefits as determined by the U.S. Department of Labor. California's own prevailing wage law (Labor Code) governs state and local public works.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:
- A city hires a contractor for a $50,000 public sidewalk repair. Regarding prevailing wages, the contractor must:
- A contractor on a public works project willfully fails to produce certified payroll records after proper written request. The contractor may face:
- The performance bond on a public works project protects the:
- DIR public works contractor registration generally must be:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must: