公共工程第 1598 / 1632 题

On a federal public works project, the prevailing wage requirement comes primarily from the:

a.The Uniform Commercial Code, article 2, covering materials
b.The California Labor Code, which follows the project
c.The federal Davis-Bacon Act and its wage determinations
d.The Contractors State License Law, through §7108

解析

On a federally funded construction contract above the statutory threshold, the Davis-Bacon Act requires the locally prevailing wages and fringe benefits determined by the U.S. Department of Labor. California's Labor Code prevailing wage scheme attaches to state and local public works; it does not travel onto a federal project merely because the work is in California. Article 2 of the Commercial Code governs sales of goods and says nothing about wages. B&P §7108 concerns diversion of funds by a licensee, not wage rates.

法律依据: 40 U.S.C. §3142 (Davis-Bacon Act)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈