公共工程第 1601 / 1632 题

A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:

a.Wait for the awarding body to pay it out of retention
b.Record a mechanics lien against the public building
c.Obtain the public agency's written approval to be paid
d.Give any required notice and sue on the bond in time

解析

Because public property cannot be liened, the unpaid subcontractor's security is the prime's payment bond: it must give any preliminary notice its position requires and then sue on the bond, which Civil Code §9558 allows any time after it stops work but no later than six months after the stop-notice period in §9356 closes. Recording a lien against the school or city building is void from the start. Retention is money owed the prime under the prime contract, not a fund the agency pays claimants from. No agency consent is needed or available; the bond is a contract with the surety.

法律依据: Civil Code §9558; §9356

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈