公共工程第 1601 / 1605 题
A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
a.Do nothing; payment is automatic
b.Obtain the public agency's permission to be paid
c.Record a mechanics lien against the public building
d.Give any required statutory notice and file the bond claim within the applicable time limits
解析
Because public property cannot be liened, an unpaid sub pursues the payment bond. The claimant must give any required preliminary/statutory notice and file suit on the bond within the applicable limitations period. Timely notice and filing are essential to recover on the bond.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- On a federal public works project, the prevailing wage requirement comes primarily from the:
- The performance bond on a public works project protects the:
- DIR public works contractor registration generally must be:
- When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
- On a public works project, the prevailing wage obligation applies to:
- The main reason competitive sealed bidding is used for public works is to: