公共工程第 1602 / 1605 题
When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
a.Employer payments for bona fide fringe benefits (health, pension, vacation, training) toward the total prevailing wage obligation
b.The contractor's overhead
c.Meals provided to workers
d.Only cash paid, never benefits
解析
Labor Code §1773.1 lets employers count qualifying fringe benefit contributions (health/welfare, pension, vacation/holiday, apprenticeship training) toward the total prevailing wage obligation. The worker must still receive at least the required total of cash wage plus creditable benefits.
法律依据: Labor Code §1773.1免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- The performance bond on a public works project protects the:
- DIR public works contractor registration generally must be:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
- On a public works project, the prevailing wage obligation applies to:
- The main reason competitive sealed bidding is used for public works is to:
- A public agency may reject all bids on a public works project when: