Under California's Subletting and Subcontracting Fair Practices Act, a prime bidder on public works must list in its bid each subcontractor who will perform work exceeding a threshold percentage. The main purpose is to prevent:

a.Payment of prevailing wages to the listed subcontractors
b.The prime from self-performing any part of the work
c.Bid shopping and bid peddling after the award
d.Unlicensed subcontractors from working on public jobs

解析

The Subletting and Subcontracting Fair Practices Act makes the prime name, in its bid, every subcontractor whose work exceeds one-half of one percent of the total bid, so the prime cannot shop those prices down after award or let rivals peddle lower ones in. Prevailing wage duties come from Labor Code §1771 and apply whether or not a sub is listed. Self-performance is not restricted by the Act; listing is required only for work actually subcontracted. Licensing is policed by the CSLB and by §4104's licence-number requirement, which is a detail of listing rather than its purpose.

法律依据: Public Contract Code §4104; §4107

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈