保险与留置权第 1535 / 1632 题

A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:

a.Triggering 30 days for other claimants and 60 days for the direct contractor
b.Triggering 60 days for other claimants and 90 days for the direct contractor
c.Leaving every claimant with 90 days from actual completion of the work
d.Extending each claimant's deadline to one year from the recording date

解析

A recorded notice of cessation has the same effect as a notice of completion: Civil Code §8414 cuts claimants other than the direct contractor to 30 days after recording, and §8412 gives the direct contractor 60 days. (b) swaps the two figures, and reversing them is the most common error on this pair. (c) is the rule when nothing is recorded — 90 days after completion for everyone — and is exactly what the recording is meant to shorten. (d) confuses this with the §8460 outer limit for bringing a foreclosure action after a lien is recorded.

法律依据: Civil Code §8412 / §8414

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈