保险与留置权第 1536 / 1605 题
'Completed operations' coverage under a CGL policy is important to contractors because it covers:
a.Injuries to the contractor's employees
b.The contractor's business income
c.Bodily injury or property damage arising from the contractor's work AFTER the job is finished and turned over
d.Theft of materials before installation
解析
Completed operations coverage responds to third-party injury or property damage arising out of the contractor's completed work after it has been finished and turned over to the owner — critical for latent construction defects that appear post-completion.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A subcontractor's certificate of insurance names the general contractor as 'certificate holder.' Being a certificate holder means the general contractor:
- On a private work of improvement, when a valid payment bond has been recorded, an unpaid subcontractor may:
- A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
- A sole-owner contractor with no employees wants to avoid carrying workers' compensation insurance. Generally, the contractor may:
- To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
- Which best explains why a general contractor requires each subcontractor to carry its OWN workers' compensation insurance?