To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
a.Assignment of the lien to a lender
b.Extension of credit, which extends the time to sue up to one year from recording
c.Automatic renewal every 90 days
d.Increase in the lien amount
解析
Under Civil Code §8460, the parties can record a notice of extension of credit that extends the deadline to bring the foreclosure action, but in no event beyond one year after the lien was recorded. Absent such an agreement, suit must be filed within 90 days.
法律依据: Civ. Code §8460免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
- 'Completed operations' coverage under a CGL policy is important to contractors because it covers:
- A sole-owner contractor with no employees wants to avoid carrying workers' compensation insurance. Generally, the contractor may:
- Which best explains why a general contractor requires each subcontractor to carry its OWN workers' compensation insurance?
- The 125% bond required to accompany a stop payment notice served on a construction LENDER exists to:
- Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?