保险与留置权第 1541 / 1632 题
Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?
a.The subcontractor
b.The material supplier
c.The surety company
d.The project owner
解析
On a performance bond, the obligee is the party protected by the guarantee of completion — typically the project owner. The contractor is the principal and the bonding company is the surety. Subs and suppliers are protected instead by the payment bond.
免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
- Which best explains why a general contractor requires each subcontractor to carry its OWN workers' compensation insurance?
- The 125% bond required to accompany a stop payment notice served on a construction LENDER exists to:
- The recorded mechanics lien must be served on the owner within what time relative to recording, along with the Notice of Mechanics Lien?
- A hold-harmless clause where a subcontractor agrees to indemnify the general contractor even for the GC's OWN active negligence is:
- Civil Code §2782 generally makes VOID a construction contract provision requiring one party to indemnify another for that other party's:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)