保险与留置权第 1544 / 1605 题
California Civil Code §2782 generally makes VOID a construction contract provision that requires one party to indemnify another for the latter's:
a.Failure to obtain a permit
b.Delay in completing the work
c.Sole negligence or willful misconduct
d.Payment of subcontractors
解析
Civil Code §2782 voids provisions purporting to indemnify a promisee against liability for the promisee's own sole negligence or willful misconduct in construction contracts. This protects lower-tier parties from being forced to cover another party's independent fault.
法律依据: Civ. Code §2782免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Which of the following parties is typically the OBLIGEE on a contractor's performance bond for a private project?
- The recorded mechanics lien must be served on the owner within what time relative to recording, along with the Notice of Mechanics Lien?
- A hold-harmless clause where a subcontractor agrees to indemnify the general contractor even for the GC's OWN active negligence is:
- A 'primary and noncontributory' insurance requirement in a subcontract means that when the sub names the GC as additional insured, the sub's policy should:
- On a private project with no notice of completion or cessation recorded and the work simply finished, ALL claimants (direct contractor, subs, and suppliers alike) have how long to record a lien?
- Why might an owner prefer that the general contractor obtain a payment bond rather than rely solely on the contractor to pay subs?