保险与留置权第 1545 / 1632 题
A subcontract requires 'primary and noncontributory' coverage when the sub names the GC as additional insured. That means the sub's policy should:
a.Not respond to the general contractor's own claims at all
b.Pay first, without contribution from the GC's policy
c.Pay only after the GC's own policy has been fully exhausted
d.Cover the sub's employees for their own injuries
解析
Primary and noncontributory means the subcontractor's policy answers first for claims arising out of the subcontractor's work, and does not ask the additional insured's own insurer to share the loss — which is what makes the risk transfer real rather than nominal. (c) is the excess or umbrella position, the exact inverse of what the requirement buys. (a) describes where the general contractor stands with no additional insured endorsement at all. (d) is workers' compensation, a coverage no liability endorsement supplies.
法律依据: —免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- The recorded mechanics lien must be served on the owner within what time relative to recording, along with the Notice of Mechanics Lien?
- A hold-harmless clause where a subcontractor agrees to indemnify the general contractor even for the GC's OWN active negligence is:
- Civil Code §2782 generally makes VOID a construction contract provision requiring one party to indemnify another for that other party's:
- On a private project with no notice of completion or cessation recorded and the work simply finished, ALL claimants (direct contractor, subs, and suppliers alike) have how long to record a lien?
- Why might an owner prefer that the general contractor obtain a payment bond rather than rely solely on the contractor to pay subs?
- 'Inland marine' insurance for a contractor most commonly covers: