保险与留置权第 1546 / 1605 题

On a private project with no notice of completion or cessation recorded and the work simply finished, ALL claimants (direct contractor, subs, and suppliers alike) have how long to record a lien?

a.30 days from completion
b.60 days from completion
c.One year from completion
d.90 days from completion

解析

When no notice of completion or cessation is recorded, Civil Code §8412 and §8414 give every claimant 90 days after actual completion to record a mechanics lien. The 30/60-day distinctions apply only once such a notice is recorded.

法律依据: Civ. Code §8412

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈