After a home improvement contract is signed, when must the contractor give the homeowner a copy?

a.Only upon the homeowner's written request
b.After the first progress payment is made
c.Within 10 days of signing
d.Before any work begins, when the contract is signed

解析

B&P §7159 requires the contractor to furnish the buyer a fully completed, signed copy of the contract before any work is performed.

法律依据: B&P §7159(a)