合同与履行第 703 / 1605 题

After a home improvement contract is signed, when must the contractor give the homeowner a copy?

a.Only upon the homeowner's written request
b.After the first progress payment is made
c.Within 10 days of signing
d.Before any work begins, when the contract is signed

解析

B&P §7159 requires the contractor to furnish the buyer a fully completed, signed copy of the contract before any work is performed.

法律依据: B&P §7159(a)

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈