合同与履行第 705 / 1632 题
Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?
a.The homeowner must be a senior citizen
b.The contractor must be paid in full in advance
c.The contract price must exceed $2,500
d.The buyer must have initiated contact requesting the work
解析
Under B&P §7159.10, a service and repair contract may be used only when, among other conditions, the buyer initiated contact to request the work and the price is $750 or less.
法律依据: B&P §7159.10免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
- After a home improvement contract is signed, when must the contractor give the homeowner a copy?
- A change order that increases the price of a home improvement project by $3,000 is agreed to verbally on-site. To be enforceable under §7159, the change order must be:
- What is the maximum contract amount for a job to qualify as a 'service and repair' contract under §7159.10?
- Under a valid service and repair contract, when may the contractor collect payment from the homeowner?
- A contractor collects a $2,500 down payment on a $15,000 room addition. Why is this unlawful?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对