A change order that increases the price of a home improvement project by $3,000 is agreed to verbally on-site. To be enforceable under §7159, the change order must be:
a.Witnessed by the project inspector
b.Recorded with the county recorder
c.Approved by the CSLB in advance
d.In writing and signed by both parties
解析
B&P §7159 requires that any change to a home improvement contract be in writing and signed by both the contractor and the owner before the extra work is done.
法律依据: B&P §7159(c)免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Which of the following is a mandatory element that must appear in every written home improvement contract?
- A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
- After a home improvement contract is signed, when must the contractor give the homeowner a copy?
- Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?
- What is the maximum contract amount for a job to qualify as a 'service and repair' contract under §7159.10?
- Under a valid service and repair contract, when may the contractor collect payment from the homeowner?