合同与履行第 887 / 1632 题

In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:

a.A signed liquidated damages clause in the agreement
b.Photographs of the contractor's trucks on the site
c.Daily records of labor hours and materials, with receipts
d.A copy of the contractor's active licence, and nothing else

解析

A time-and-materials contract prices the work by inputs, so an invoice is worth exactly what the record behind it is worth: dated daily logs of who worked and for how many hours at which agreed rate, what material arrived, and the supplier invoices proving it. B&P §7159.10(e)(7) shows the same logic in statute for a service-and-repair job estimated on time and materials — the contract must disclose the set rate, the estimated cost of materials, and how time is computed, in quarter hours, half hours or hours. (a) is irrelevant to proving work done; liquidated damages fix the consequence of a breach in advance. (d) proves a precondition to suing at all under B&P §7031, not the amount owed. (b) documents attendance, not hours, rates, or materials.

法律依据: Bus. & Prof. Code §7159.10(e)(7); cf. §7031

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈