A key reason a contractor should ensure the person signing a contract has authority to bind the property is that:
解析
Signing the wrong person costs the contractor twice. The contract binds only the party who signed, so a tenant, a property manager or one co-owner acting alone can leave the contractor with no claim against the person who owns the property — and the mechanics lien is no rescue, because Civil Code §8444 lets an owner who did not contract for the work record a signed and verified notice of nonresponsibility and take the fee interest out of reach. For a home improvement contract, B&P §7159(d) requires the writing to be signed by the parties to the contract, so who signs is a compliance question as well as a collection one. (b) is backwards: less certainty about who is bound makes a written scope more necessary, not less. (c) and (d) are invented — public works status turns on public funds and a public awarding body, and no signature sets a price.
法律依据: Civil Code §8444; Bus. & Prof. Code §7159(d)免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- A contractor and owner sign a contract, then later sign a separate written agreement that clearly changes the completion date and adds $6,000 in scope. This later signed agreement is best described as:
- In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:
- An owner and contractor dispute whether a certain task was included in the fixed price. The contract's clear, integrated scope of work does not list that task. Under general interpretation principles, the task is most likely:
- Overall, the single most effective way for a contractor to prevent and win contract disputes over scope, extras, and payment is to:
- 某装修承包商用于独栋住宅的印刷版合同中,仲裁条款与全文一样是 9 磅字号,标题写作「争议解决」,也没有留出业主单独签名缩写的位置。依《商业与职业法》第 7191 条,该条款效力如何?
- 某总承包商的标准分包合同要求分包商就工程中发生的一切损失向总包赔偿,包括完全由总包自身过失造成的损失。依《民法典》第 2782 条,该赔偿条款:
最近核对: · 审核流程