Contracts & ExecutionQuestion 702 of 1605
A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
a.Acceptable if filled in later that day
b.A prohibited act and grounds for disciplinary action
c.Allowed if the homeowner initials each blank
d.Allowed for repeat customers
Explanation
B&P §7161 makes it a prohibited act (and cause for discipline) to cause a buyer to sign a contract containing blank spaces to be filled in after signing.
Law Reference: B&P §7161Practice all 1605 questions free — no signup required.
Related questions on this topic
- Which document, warning homeowners that unpaid subcontractors and suppliers may place a claim against their home, must be included in a home improvement contract?
- A home improvement contract states the project 'will start sometime soon and finish when done.' What is the defect?
- Which of the following is a mandatory element that must appear in every written home improvement contract?
- After a home improvement contract is signed, when must the contractor give the homeowner a copy?
- A change order that increases the price of a home improvement project by $3,000 is agreed to verbally on-site. To be enforceable under §7159, the change order must be:
- Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)