Contracts & ExecutionQuestion 703 of 1605

After a home improvement contract is signed, when must the contractor give the homeowner a copy?

a.Only upon the homeowner's written request
b.After the first progress payment is made
c.Within 10 days of signing
d.Before any work begins, when the contract is signed

Explanation

B&P §7159 requires the contractor to furnish the buyer a fully completed, signed copy of the contract before any work is performed.

Law Reference: B&P §7159(a)

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report