Contracts & ExecutionQuestion 703 of 1605
After a home improvement contract is signed, when must the contractor give the homeowner a copy?
a.Only upon the homeowner's written request
b.After the first progress payment is made
c.Within 10 days of signing
d.Before any work begins, when the contract is signed
Explanation
B&P §7159 requires the contractor to furnish the buyer a fully completed, signed copy of the contract before any work is performed.
Law Reference: B&P §7159(a)Practice all 1605 questions free — no signup required.
Related questions on this topic
- A home improvement contract states the project 'will start sometime soon and finish when done.' What is the defect?
- Which of the following is a mandatory element that must appear in every written home improvement contract?
- A contractor asks a homeowner to sign a home improvement contract that still has blank spaces for the price and scope of work. Under the CSLB law, this practice is:
- A change order that increases the price of a home improvement project by $3,000 is agreed to verbally on-site. To be enforceable under §7159, the change order must be:
- Which of these is a condition that must be met before a contractor may use a 'service and repair' contract form instead of a full home improvement contract?
- What is the maximum contract amount for a job to qualify as a 'service and repair' contract under §7159.10?
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)