Contracts & ExecutionQuestion 704 of 1632

A change order that increases the price of a home improvement project by $3,000 is agreed to verbally on-site. To be enforceable under §7159, the change order must be:

a.Witnessed by the project inspector
b.Recorded with the county recorder
c.Approved by the CSLB in advance
d.In writing and signed by both parties

Explanation

B&P §7159 requires that any change to a home improvement contract be in writing and signed by both the contractor and the owner before the extra work is done.

Law Reference: B&P §7159(c)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report